8500 CHURCH RD

Alteration Structure type 34 $10,000
Application dateJun 2, 2026
Issue dateJun 4, 2026
Days to issue2
Estimated cost$10,000
Project typeAlteration
Structure type34
First seen2026-06-06 12:11:58

Description

Execute structural floor framing reinforcement and foundation masonry stabilization as detailed in the project blueprint. Major tasks include removing and replacing a failing segment of the main wood beam, setting 7 adjustable heavy-duty steel jack posts, sistering 16 floor joists, and applying polyurethane crack sealant and tuckpointing along the perimeter wall.