1001-3 S GRAND BLVD
| Application date | Mar 16, 2026 |
|---|---|
| Issue date | Apr 8, 2026 |
| Days to issue | 23 |
| Estimated cost | $28,000 |
| Project type | Addition |
| Structure type | 26 |
| First seen | 2026-04-20 16:02:14 |
Description
Install piping and components for foam system to feed helipad (design, foam skid and nozzles provided by others). Reference design drawings are provided under this submittal for the foam system design. Pipe configuration and routing design by EFP. New design is an addendum to existing permit 582682-24 and replaces Sheet FP1.131.